MACLENNAN-LSE WATERPROOFING were contacted by CMS, as we were already dealing with other aspects of the project

CMS had begun to excavate the Lift Pit and it began to fill with water.
MACLENNAN-LSE
WATERPROOFING advised how to construct the lift pit, and specified that an Injection hose be installed in the construction joints, and an external
Type A Vandex system ( cementitious slurry ) to be applied.

The injection tube was installed. Then CMS cast the lift pit walls.
MACLENNAN-LSE
WATERPROOFING
then returned to site and injected the hose with a Polyurethane resin and applied the
Vandex waterproof coating